This week we got most of the roof up for the second floor. We used a different type of roof on this floor. The smaller concrete beams were ordered and brought to the site. After they were placed, the bricks were fitted into the space between the beams. Lord willing, we will pour the roof this Thursday. Please pray the remaining jobs will be completed to meet that time-table!
Julio Lima from church is in charge of the second floor. Where would we be without him?!
I no longer worry about anyone climbing around. They do worry about me. If I had a dollar every time one of the men said, "Be careful Pastor!" we could probably build the third floor!
Getting ready to move the small beams up for the roof.